The Build
The Stages of Construction The site pre-build…………and the completed ‘shell’. |
|
Nov. 2013 - Feb. 2014 Negotiations held, and subsequently permission granted to build an Observatory - gained from coowners of site (Forest England, National Forest, and South Derbyshire District Council). |
|
Planning Permission granted - end of 2015. Fundraising began 2014. Target £27K. Total achieved March 2017. |
|
Dome purchased secondhand from Huddersfield - February 2014. Wide load permission for the trip home. |
|
Dome Refurbishment Working Parties - held over a number of weekends 2014 - 2017. |
|
Contractor on site November 2018 - April 2019 |
|
Site clearance - 12th November 2018 |
|
Managing the delivery of concrete |
|
The design and what we built |